Well 70, replacing Well 271

Well 70 (Replacing Well 271) is located at 7111 McHenry Avenue in Del Rio, California near the northwest corner of McHenry Avenue and Stewart Road.

As of January 8, 2019, Well 70 has been successfully drilled and constructed to a depth of 590 feet below ground surface (bgs). The well was completed with the following City of Modesto’s goals in mind:
1) Achieving a water production capacity of 1,000 gallons per minute (gpm), which will help improve the overall water capacity of the Del Rio community.
2) Produced water quality meeting all current drinking water standards.

Key Project Dates:

Well 70 – Below Ground Construction

Drilling Construction Operations Initiated (September 10, 2018)
Construction Completed (January 8, 2019)

Next Steps for the Well 70 - Above Ground Improvements

Final Plans & Specifications (Anticipated Date: Early March 2019)
Project Bid (Anticipated Date: Late March/Early April 2019)
Bid Opening (Anticipated Date: Mid May 2019)
Construction Start (Anticipated Date: December 2019)
Substantial Completion (Anticipated Date: Summer 2020)
Final Completion (Late Summer 2020)